Cachoeirão Dam Profile
Available Layers
Location
Countries: Brasil
Basins: Tapajós
Rivers: Juruena
Project Information
Capacity: 64 MW
Flooded Area: 3 Km2
Cost: R$ 147.2 million
Operational Status: Planned
Companies Involved: Centrais Elétricas do Norte do Brasil S/A (Eletronorte) / Linear Participações e Incorporações Ltda. / Maggi Energia S/A / MCA Energia e Barragem Ltda.
More Information
Companies:
- Eletronorte is a federal state-owned company controlled by the holding Eletrobrás.
- Maggi Energia S/A is part of the group Andre Maggi.
Timeline:
Federal Government expects the plant to start operating in 2013.
Links:
- Stop the machines
- Linear Participações e Incorporações Ltda. and MCA Energia e Barragem Ltda. are subject to juridical action due to the practice of labor analogous to slavery.